How do megaprojects
keep every step in order?
Can't play sound? The illustrated version is right below.
Read the transcript
The full narration of the video.
Thousands of people build one tower. Who goes first, and how does it not turn into chaos? First, an honest note: big projects are not foolproof. One researcher went through big projects worldwide, and nine out of ten ended up over budget.
Their real skill is keeping the order straight, and catching mistakes early. To plan the order, start from the last day and think backward. Pick the handover day, then ask: what must be finished before that?
Interiors wait for walls, walls wait for floors, floors wait for columns, and columns wait for the foundation. Every job answers just one question: whose work do I wait for? Draw each wait as an arrow, and you get a web.
It's a lot like cooking a big holiday dinner. The braised pork needs cutting, blanching, then two hours of stewing, step after step, the longest chain. The cucumber salad takes ten minutes, anytime is fine.
When dinner is served depends on that longest chain. Construction is the same. The longest path of arrows is called the critical path. Any job on that path that slips a day delays the whole building a day; other jobs have slack, and can slip two days without harm.
Site offices often pin up a long chart called a Gantt chart: one row per job, one bar for how many days it takes. The bars on the critical path are often marked in red, and whichever one slows down gets more workers first. With the order right, one more thing to guard against: something missed.
The scariest misses are things about to be covered up. Pipes and wires in the walls, steel bars in the floors, once the concrete goes on, you never see them again. So in China, the rule is: before anything is covered, the builder must call in the owner and the quality inspectors.
This is called concealed work inspection. Without the supervising engineer's signature, the next step may not begin. Many projects now go one step earlier: before breaking ground, they build the whole tower on a computer. A pipe hitting a beam, an air duct that won't fit, it all shows up on screen.
Fixing it on a computer takes a few clicks; fixing it in a finished building means breaking walls. So big projects don't rely on never making mistakes. They rely on drawing the waits as a web, watching the longest path, and stopping for a signature at every spot that's about to be covered.
Next time you renovate, before the walls close over the plumbing and wiring, have someone check it too. If you've worked on a site, which job did you most dread having to redo?
First, the honest part
A researcher looked at megaprojects around the world: nine out of ten went over budget. So big projects are not foolproof.
Their real skill is
keeping the order straight,
and catching mistakes early.
People have planned builds like this for thousands of years. Think of the Great Pyramid: over two million stones, laid one by one.
Start from
hand-over day
Pick the day you hand over the keys, then ask: what must be done before that? Finishing waits for the walls. Walls wait for the floors. Floors wait for the columns. Columns wait for the foundation.
Every job asks one thing:
who am I waiting for?
Draw each "wait" as an arrow and you get a network. Plumbing, wiring and lifts can run alongside other jobs, so it is a web, not a single line.
Like cooking a big
holiday dinner
The longest chain decides when dinner is served. (In China this is the New Year's Eve feast.) One cook runs a kitchen, but a site has dozens of crews at once, so they draw the web and check it every week.
The longest path is
the critical path
The longest chain of arrows in the web is the critical path. If any job on it slips one day, the whole building slips one day. Other jobs have slack; two days late changes nothing.
Look inside a site office and you will often see a long chart on the wall, a Gantt chart: one row per job, one bar for the days it takes. Bars on the critical path are often marked in red.
If a red bar is slow,
that is where extra workers go.
Before a wall is closed,
someone must sign
no next step Pipes and wires in walls, steel bars in floors: once concrete goes on, nobody can see them again. So in China the builder must call the owner and the quality inspectors to check before anything is covered. This is called a concealed-work inspection.
It is in Articles 30 and 37 of China's Regulations on the Quality Management of Construction Projects.
Build it once
on the computer first
Many projects now go one step earlier: they build the whole building on a computer first (this is called BIM). A pipe hitting a beam, or an air duct that will not fit, shows up on screen.
On a computer, a fix is a few clicks.
In a finished building,
it means breaking walls.
They draw the web, watch the longest path, and get a signature before anything is covered.
Quick check
What mainly decides how long a building takes?
Like a holiday dinner: the braised pork that simmers for two hours decides when you eat; the cucumber salad can be made anytime.